Gree sued the Guangzhou Bureau of Finance quote low but unsuccessful – Gree, Gre

Central Hospital in Guangzhou City Panyu
Air conditioning
Installation of government procurement projects, offer 17.07 million yuan in Guangzhou, Gree air-conditioning
Sell
Co., Ltd. (hereinafter referred to as "Gree air-conditioning") is lost to offer 21.51 million yuan of
Guangdong
Province
Oil
Chemical industry
Construction Corporation, the government spend 400 million dollars for Air. To this end, Gree air-conditioning to the Guangzhou Municipal Bureau of Finance to court to challenge the government procurement sector waste of public money, "Are the taxpayers have no place to spend more money to spend does not go out?"

The case yesterday (November 2, 2009) in the Tianhe District Court hearing.

Events

Unexpected turn: the highest price offered in the

"Not the first serious review before so Gree luck with the first."?? Municipal Finance Bureau

"Do the taxpayers have no place to spend more money to spend does not go out?"?? Attorney Gree Air Conditioning

2008 11 4, Gree air-conditioning for the tender for sale of commercial air conditioning Minister Xujun Ming is a day for rejoicing, because the central hospital in Panyu in the procurement bidding, Gree air-conditioning to the tender offer 17,070,000 element is the bid evaluation committee recommended to become the first party candidate. If there is no accident, then it means winning the.

But empty a joy.

2008 11 21, won the bid results published previously ranked No. 1, the lowest bidding Gree air conditioner is excluded, and offer the highest building in Guangdong Petrochemical Corporation won the bid, which marked more than the Gree Air conditioning a full high four million yuan.

Gree air-conditioning, said: "Both the tender offer, or technical, financial status, reputation, performance, and we are more competitive, but we are not elected."

Strange reason: Word Error
Gree Air Conditioning
dissatisfied, to the Panyu District Finance Bureau
Complaints
. So why would defeat it?

Reply Panyu District Financial Bureau, Gree air-conditioning is not standard bidding documents and should not be successful. District Financial Bureau dismissed the complaints of Gree air-conditioning.
Gree Air Conditioning Youxiang
Finance Bureau, Guangzhou, filed for administrative reconsideration, the Guangzhou Bureau of Finance to make an administrative reconsideration decision to revoke the deal, Panyu District Financial Bureau decision, and ordered to re-finance bureau Panyu District, an administrative decision.

2009 6 8, Panyu District, Bureau of Finance in the Government Procurement Experts database to verify the collected seven-member evaluation panel, to verify the result, six experts Gree air conditioner tender documents of tender documents do not meet the target request an expert that can basically meet the requirements.

In accordance with the principle of majority to verify the group concluded that: Gree air-conditioning the tender documents, tender documents does not meet the requirements. Accordingly, the Panyu District of Finance once again dismissed the complaint Gree air-conditioning.
Gree Air Conditioning Youxiang
Finance Bureau for review, Guangzhou, Guangzhou, Panyu District Finance Bureau of Finance to maintain the new decisions of administrative reconsideration decision.

Last year, things are still back where we started.

Xujun Ming said: "If the text-error argument that business out in the bidding, would be too picky. The Government procurement tenders in order to save money, but now gives the impression that the tender procurement would rather spend more 4 million, a business will not listen, the wrong interpretation of the text. "

Satisfied with the results of Gree air-conditioning, the prosecution of the Guangzhou Municipal Bureau of Finance.