Burnley Tunnel

History

The tunnel was constructed between 1996 and 2000 by Transfield-Obayashi Joint Venture. Prior to its opening to traffic, the tunnel was opened to the public to walk through from Southbank to Burnley, on 16 December 2000.

The tunnel was opened to traffic on 22 December 2000. In February 2001 it was found that a wall panel was cracked with 5 litres of water a second entering the tunnel. The cause was later found to be floor sections lifting from water pressure, and modifications to correct this being approved in November 2001. Also in 2001 Transfield Obayashi Joint Venture agreed to pay Transurban $157 million in damages in an out-of-court settlement over late completion of the tunnel.

Transurban launched further legal action against the Transfield Obayashi Joint Venture in 2007, after radar tests indicated the tunnel walls were thinner than that specified in the contract, possibly resulting in the tunnel not lasting for the proposed 100-year design life. Further tunnel leaks were also discovered in 2007, but were unrelated to the tunnel fire.

2007 fire

On 23 March 2007 just before 10 am, a pile-up occurred in the tunnel involving three trucks and four cars. The crash resulted in an explosion and a subsequent fire which reached temperatures in excess of 1,000 C (1,832 F) according to firefighters, and forced the evacuation of motorists from both the Burnley and nearby Domain tunnels. Three people died in the accident. One was Australian Olympic cyclist Damian McDonald, who won a gold medal in the road team time trial at the 1994 Commonwealth Games in Victoria, Canada, and also represented Australia at the 1996 Summer Olympics. Another was Darren Hartley Sporn, a father of two daughters, who owned a plumbing business. Approximately 400 people were advised by the tunnel’s safety system to abandon their cars, to leave their keys in the ignition, and to evacuate the tunnel after the collision.

The accident occurred after a truck broke down in the left hand lane. Safety systems allegedly closed the left lane and a response vehicle was on its way to assist the broken-down truck. Two cars traveling in the left hand lane had come up behind the broken-down truck and were attempting to merge into the center lane. Another truck traveling in the left lane came up behind them and also attempted to merge to the right, but it failed to either stop behind the stationary vehicles or merge successfully. It then collided with vehicles in both the left and middle lanes, resulting in a multi-vehicle pile up involving 4 cars and three trucks. It is believed an explosion resulted from the ignition of a ruptured fuel tank of a vehicle involved in the crash. Other reports of the details vary, however.

Fire suppression system test before tunnel opening in December 2000

The following traffic came to a stop and approximately 200 vehicles became stranded inside the tunnel. The Public Address & Radio Rebroadcast Systems advised motorists to turn off their ignition, leave the keys in, and to evacuate the tunnel. Emergency exits are located throughout the tunnel and lead to separate pedestrian tunnels. Some motorists walked the 1km back along the roadway to the western tunnel entrance. Approximately 400 people were evacuated, three of whom were taken to hospital. Hundreds waited at the tunnel’s west entrance until emergency services advised it was safe to remove their vehicles. The tunnel suffered some damage to cables and other internal infrastructure, but is believed the structure was undamaged by the fire.

Eighty-four firefighters responded within five minutes of the crash occurring and emergency personnel were able to gain access to the Burnley tunnel on foot via a separate emergency tunnel linking the Burnley to the Domain tunnel. Fire hoses were carried through to the crash site while emergency vehicles were stationed in the Domain Tunnel. A number of fire appliances were transported contra-flow from the exit portal of the tunnel to the crash site. The deluge system was activated instantly and this was deemed by firefighters to have greatly aided in keeping the fire under control. The nozzles used in the deluge system were manufactured by BETE Fog Nozzle. The smoke extraction system functioned as planned and removed toxic fumes from the tunnel and out into the open air. Smoke was vented to the ventilation stack in Southbank.

Metropolitan Ambulance Service Paramedics were sent in to treat evacuees if required. St John Ambulance Australia emergency medical teams were also put on standby in case the accident was deemed as a major disaster and many more injured and fatalities had arisen.

Design

Interchange consisting of the Burnley Tunnel entrance, Domain Tunnel entrance, Westgate freeway and Power Street/Kings Way ramps.

The Burnley Tunnel is 3.4 kilometres (2.1 mi) long and comprises 460 metres (1,509 ft) of cut and cover at the west portal, 2.84 km (1.76 mi) of driven tunnel, and 180 m (591 ft) of cut and cover at the east portal. The gradient at the west end is 6.2% downhill for traffic, then relatively level until a 5.2% grade out of the tunnel. During construction a shaft located at the midpoint of the tunnel was used to speed up work, as it provided another two working faces for the roadheaders used. The shaft is today used for ventilation and emergency egress, in addition to a 1,420-metre (4,659 ft) long pedestrian tunnel that parallels the eastern part of the tunnel. Eight cross passages link the main and emergency tunnels, two more cross connects provide an emergency exit to the Domain Tunnel, and two emergency refuges are also located in the tunnel. Unlike the shallower and shorter Domain Tunnel, it passes deep under the Yarra River. It was subject to significant engineering problems and delays during construction due to unexpectedly high water pressures at its maximum depth of 65 m (213 ft).

A variable speed limit applies to traffic in the tunnel. In normal circumstances the speed limit is 80 km/h (50 mph), but a 40 km/h (25 mph) speed limit applies during maintenance. The speed limit during peak periods is often reduced to 60 km/h (37 mph) to prevent unnecessary congestion at the Monash Freeway. Regular radio transmissions can be received while in the tunnel because many radio stations have installed their own transmitters. Normal radio broadcasts can be interrupted by management announcements over all channels.

References

^ “Mysterious crack floods Melbourne’s CityLink tunnel”. 7.30 Report. www.abc.net.au. 22 February 2001. http://www.abc.net.au/7.30/stories/s250493.htm. Retrieved 8 July 2008. 

^ “Melbourne CityLink Burnley Tunnel cost fight”. tollroadsnews.info. 22 January 2007. http://tollroadsnews.info/artman/publish/article_1701.shtml. Retrieved 8 July 2008. 

^ “Transurban action over tunnel walls”. Sydney Morning Herald. smh.com.au. 23 January 2007. http://www.smh.com.au/news/business/transurban-action-over-tunnel-walls/2007/01/22/1169330827274.html. Retrieved 8 July 2008. 

^ “Burnley Tunnel leaks again”. Herald Sun. www.news.com.au. 18 July 2007. http://www.news.com.au/heraldsun/story/0,21985,22093019-2862,00.html. Retrieved 8 July 2008. 

^ a b “Cars reduced to balls of metal in tunnel fire”. The Age. 23 March 2007. http://www.theage.com.au/news/general/motorists-flee-tunnel-fire/2007/03/23/1174597835500.html. Retrieved 23 March 2007. 

^ “Family mourns the loss of Olympian”. News Limited. 23 March 2007. http://www.news.com.au/story/0,23599,21442542-2,00.html. Retrieved 25 March 2007. 

^ a b Jian Zhao, Zhao, J. Nicholas Shirlaw, Rajan Krishnan (2000). “Tunnels and Underground Structures”. Taylor & Francis. pp. pages 158-9. http://books.google.com.au/books?id=KuUtzTWzN-8C&pg=PT178&lpg=PT178&dq=Domain+Tunnel+history&source=web&ots=pYAPScwt5k&sig=ztzh-005nq2UwyMEYAhd29Y80no&hl=en&sa=X&oi=book_result&resnum=4&ct=result#PPT179,M1. Retrieved 8 July 2008. 

External links

news.com.au images

v  d  e

Crossings of the Yarra River in Melbourne

Spotswood sewer tunnel  West Gate Bridge  Bolte Bridge  Webb bridge  Charles Grimes Bridge  Spencer Street Bridge  King Street Bridge  Queens Bridge  Sandridge Bridge  Southbank Footbridge  Princes Bridge  Swan Street Bridge  Burnley Tunnel  Domain Tunnel   Morell Bridge  Hoddle Bridge  Cremorne Rail Bridge  Church Street Bridge  MacRobertson Bridge  Glen Waverley Line  Monash Freeway  Swan Street  Alamein, Belgrave & Lilydale Lines  Hawthorn Bridge  Victoria Bridge  Johnston Street Bridge  Eastern Freeway

Categories: Bridges in Melbourne | Tunnels in Australia | Tunnels in Victoria (Australia) | Toll roads in Australia | Transport in Melbourne | Buildings and structures in Melbourne | Crossings of the Yarra River

I am China Crafts Suppliers writer, reports some information about mini disco ball , ellipsoidal lights.

Processing your request, Please wait....

Leave a Reply