Henan Highway 15 key projects have been started full speed – Henan, project and

Key projects in Henan Province is in full speed: Zheng Western passenger line Track Road laying has been Completed, this month plans to begin paragraphs Zhengzhou to Luoyang The testing; Zheng Jiao inter-city project for the Yellow River Bridge project started construction in mid and late 11; hippocampus (Zhengzhou) 150 000 sedan assembly plant project already has a water , electricity, gas conditions … … 24, the Provincial Development and Reform Commission has released 7 months ago in Henan Province construction of key projects: 1 July, the provincial key projects accumulated 86.26 billion yuan, accounting for 66.4% of the annual target were started Project 73, completed 23 projects.

Zheng Luo Zheng special section of the West customers to debug this month
Rail, 1 to 7 months to complete investment 17.95 billion yuan, accounting for 45% of the annual target.

This year on June 29, planned completion of track laying Cheng West passenger line has been Completed, currently under way along the new civil station Construction And equipment installation, in accordance with the plan, beginning this month in Zhengzhou to Luoyang The testing section. Container logistics center in Zhengzhou Railway Station laying, Communicate Lines, have been completed, the completion of 94% power lines, is expected to be completed this month. Zhengzhou Railway Station West Export Renovation project, plans completed by the end.

Zheng new Yellow River Bridge has been completed 63% of the beam assembly. According to Henan Province Transportation Office official Website Introduced February 13, 2010, Zheng ensure that the new Yellow River Bridge through the main bridge deck. Cheng Xu

program started off special projects, National Development and Reform Commission was July 12 ~ 13 project proposals were evaluated, Henan Province led to the NDRC and the evaluation Expert Group reported in detail by the city of Mount John station alignments Dangshan views, but also the communication with relevant parties in Anhui Province.

Henan Province will accelerate the implementation of Central City Group Rail Transit Construction. Zheng Jiao for inter-city railway, July 9, the Provincial Development and Reform Commission jointly with relevant departments and Zhengzhou, Jiaozuo cities were on the Bridge Site convergence towards the Yellow River Bridge project started construction in mid to late 11. Cheng, intercity rail, Design Institute of Ministry of Railways has arranged by rail from standard to standard changes by inter-city rail pre-feasibility study.

15 high-speed Highway Project has been started
Highways, 1 to 7 months to complete investment 5.06 billion yuan, accounting for 51% annual target.

Continued construction of the Beijing-Hong Kong and Macao rapid progress of high-speed reconstruction and extension project, Zhengzhou Luohe subgrade earthwork has been completed some 93%, bridge pile some 99% have been completed. Anyang to Xinxiang subgrade earthwork has been completed some 99%. The new village of Cai to

(Yu-wan sector), Gongyi to Dengfeng program started from 15 highway projects had been realized-point start, are actively promoting the construction preparation work, and strive to set off as soon as possible upsurge in construction. Within the village to work on for the end of Dengzhou Highway, being the land pre-and EIA. Luoyang to Song County Highway is compiling. Jiao Tong speed Wenxian to Gongyi, Dengfeng to Yu Chau section, environmental impact assessment, water conservation, geological and pressure mines, seismic evaluation has been the assessment.

Text Museum Decoration Basically completed Social cause Item 1 to 7 months to complete investment of 1.49 billion yuan, accounting for 55% of the annual target.

Museum of Chinese characters basically completed the decoration, outdoor road, square green under construction.
Plans 5 new projects this year. Provincial Maternal and Child Health Hospital maternity ward floor, Xuanzang hometown Buddha cultural tourism projects, the provincial hospital wards floor staff, Provincial Party School reconstruction project of an other four project has been started. Provincial People's Hospital New Ward Building program started in August.

Industrial projects, the hippocampus (Zhengzhou) 15 million cars had been completed for 82% of annual targets, assembly plant already has the water, electricity, gas conditions.